Nyrstar Alternative Feed and Blast Furnace Shutdown 2018
Contract Name
Nyrstar Shut Down 2018
Date Completed
June 2018
Client
Nyrstar
Detailed Scope and Description
- Supply of cranes from 2.5t mini crawler to 400t all-terrain crane
- Working day and night shift
- Demolition and replacement of the alternative feed system for the plant
- Major works in the blast furnace
- Total crane management including lift studies, and project co-ordination
Extent of involvement
- Supply of Cranes from 400t-15t with supply of riggers and support staff.
- All supervision and management and staff to co-ordinate with shut down planners/scheduler’s
Summary of OHS performance
Nil incidents and accidents