Torrens Rail Junction Development

Project

Torrens Rail Junction

Contract Name

Torrens Rail Junction – New Bowden Station

Date Completed

Feb 2018

Client

Laing O’Rourke

Detailed Scope and Description
  • Supplied cranage to lift and position several bridge beams, longest was 88m and the heaviest was 50t.
  • Crane Services was supplied plans to calculate crane requirements
  • Multiple set ups were required to achieve critical works
Extent of involvement

Produce several Lift studies with detailed information which would be used for the safe installation of all precast works

Successes / value add / lessons learnt

The continuous ongoing works of this project has resulted in the works being brought in under the allotted time detailed and specified. We have constantly been on hand to change and amend any issued that arose with this project.